Energy Independence Bill would change land access for grid works

The Bill introduced on 4 November would reform wayleaves, overhead line consents and rights of entry in Great Britain, and make installers register heat pumps, chargers and batteries with the local network operator. None of it is law yet.

£4bn Constraint costs in 2030 that faster transmission building could avoid, by NESO analysis

The government introduced the Energy Independence Bill in Parliament on 4 November 2026. It is a wide Bill: it would bring energy brokers and price comparison services under Ofgem regulation, put the Warm Homes Agency into law, end new oil and gas exploration licences and, through amendments still to come, scrap standing charges on household gas bills. For the firms that build and maintain electricity networks, the part that matters most is the reform of consents, land access and land rights. The government’s factsheet says Great Britain will need around twice as much new transmission network by 2030 as was delivered in the past decade, and that the current framework was not designed for building on that scale. It cites analysis by the National Energy System Operator (NESO) that speeding up critical transmission projects could cut constraint costs in 2030 by about £4 billion, which it puts at £40 to £50 for an average dual fuel household.

The factsheet names five areas to be modernised: wayleave applications, section 37 consents (the consent an overhead line needs), statutory rights of access to premises, works in private streets and vegetation management. The law firm Slaughter and May, in an analysis published on 16 November, reads the Bill as follows. An objection from a local planning authority to an overhead line in England and Wales would no longer automatically trigger a public inquiry, and the Secretary of State would have to publish timetables for decisions. Transmission owners would share the rights of entry that distribution companies hold, on notice of between five working days and three months, and those rights would apply to existing infrastructure whatever an existing agreement says. Applications for compulsory wayleaves that stall could be treated as withdrawn. Network companies would be responsible for keeping trees clear of their lines, planned works in private streets would no longer need consent, and landowners and occupiers would be compensated for loss or damage.

Two other measures reach the people who do the work. Installers of electric vehicle charge points, heat pumps, solar panels and domestic batteries would have a clear duty to register each installation with the distribution network operator; the government says fewer than 40% are registered today. And an amendment is promised to set up a publicly owned Great British Grid, which New Civil Engineer reports was announced by the Prime Minister in September and is expected to draw on Great British Energy’s existing budget. The union Unite said that does not go far enough and called for the grid to be renationalised. The Energy Networks Association, which represents the network companies, said record network investment could support up to 210,000 jobs across operators and their supply chains by 2035.

“Faster grid connections are welcome, but you cannot fix a broken energy system while leaving it in the hands of profiteers.”
Sharon Graham, general secretary, Unite, as reported by New Civil Engineer
“A complete restructuring of the energy sector would be costly and unnecessary.”
Lawrence Slade, chief executive, Energy Networks Association, as reported by New Civil Engineer

What it means for utility contractors

  • Nothing changes yet: the Bill has to pass both Houses of Parliament and can be amended on the way. The government says secondary legislation is needed to implement its measures in full, so today’s wayleaves, consents and notice periods still apply.
  • Access to land: on Slaughter and May’s reading, access to build and maintain lines would rest more on statutory rights with set notice periods and less on the terms of each agreement, with compensation for loss or damage. Keeping trees clear of lines would sit with the network company.
  • Registering installations: firms that fit charge points, heat pumps, solar panels or batteries would be under a legal duty to register them with the network operator. What has to be recorded, and how the duty is enforced, is left to regulations.
  • Northern Ireland and Ireland: the government’s factsheets describe the network measures in terms of Great Britain, and Slaughter and May notes the overhead line change applies in England and Wales. Northern Ireland, where energy policy is largely devolved, and Ireland have their own rules on consents and wayleaves.

This describes the Bill as introduced, from the government’s factsheets and one law firm’s reading of the text. Details may change before Royal Assent.