Guide · Construction & contractors ·
CDM duties for contractors, with Northern Ireland and Ireland compared
Who is which duty holder, when a principal contractor is needed, the construction phase plan, inductions, welfare, records and notification. With Northern Ireland’s regulations, and Ireland’s PSCS, Safe Pass and notification rules where they differ.
500 Person days, above which a project must be notified in GB, NI and Ireland
The Construction (Design and Management) Regulations 2015 apply to construction work of every size in Great Britain, domestic jobs included. Northern Ireland’s version, CDM (NI) 2016, enforced by HSENI, words the contractor duties almost identically, so this guide covers both together. Ireland’s separate system is at the end. HSE’s second five-yearly review, dated March 2026, recommended keeping CDM 2015 unchanged.
Who is which duty holder
- Client: the person or business the project is for. It appoints the team, makes sure welfare is provided and notifies the regulator where required.
- Principal designer: plans, manages and coordinates the pre-construction phase and prepares the health and safety file.
- Principal contractor: plans, manages, monitors and coordinates the construction phase. Needed whenever more than one contractor works on the project, or that is reasonably foreseeable.
- Contractor: any business that carries out, manages or controls construction work, specialists and self-employed trades included.
The client appoints the principal contractor in writing before the construction phase; if it does not, it carries those duties itself. For a householder, the client duties pass to the contractor, or to the principal contractor where there are several contractors. In England the building regulations have their own principal contractor role; one firm can hold both if the client confirms it in writing.
What the principal contractor must do
- Construction phase plan: draw it up before the site is set up, and review and revise it as the work changes.
- Coordination: plan, manage, monitor and coordinate the construction phase, organising cooperation between contractors, including successive trades.
- Inductions: make sure every worker gets a suitable site induction, specific to the site and its risks. Visitors get one proportionate to their visit.
- Site security: keep unauthorised people out of the site.
- Welfare: provide it throughout the job, to the standard set out below.
- Worker consultation: consult and engage the workers on health, safety and welfare, and let them inspect and copy the relevant information.
- Health and safety file: liaise with the principal designer and feed information into the file. If the principal designer leaves early, the principal contractor keeps the file and hands it to the client.
What every contractor must do
- The client’s duties: check the client knows them before starting work.
- Your own work: plan, manage and monitor it, and the work of anyone under your control.
- The principal contractor: comply with their directions and the parts of the construction phase plan that cover your work.
- Competence: use only people who have, or are getting, the skills, knowledge, training and experience for their tasks.
- Briefing: give your workers supervision and information, including a site induction if the principal contractor has not given one, and what to do in serious and imminent danger.
- Site and welfare: do not start until the site is secure, and meet the welfare standard for your own workers.
A sole contractor must also draw up the construction phase plan before setting up the site. The regulations name no card scheme: a card a main contractor demands is a contract term, not a CDM requirement.
The construction phase plan
The plan sets out the health and safety arrangements and site rules, with specific measures for any work on the Schedule 3 list of particular risks. These include burial or falls from height made worse by the work or site, high voltage power lines, drowning, tunnels and underground earthworks, explosives, and assembling or dismantling heavy prefabricated components. HSE says planning should be proportionate to the project’s complexity and risks: a small job needs a short plan.
Welfare
Schedule 2 of CDM 2015 (Schedule 3 in the Northern Ireland version) sets the minimum, from the start of the job:
- Toilets: enough of them, lit, ventilated and clean, separate for men and women unless each is in its own lockable room.
- Washing: beside the toilets, with hot and cold or warm running water, soap and towels, and showers where the work calls for them.
- Drinking water: a wholesome supply, with cups unless it comes from a jet.
- Changing and lockers: where workers wear special clothing and cannot change elsewhere.
- Rest: tables, seats with backs, somewhere to prepare and eat meals, a way to boil water, and a suitable temperature.
When a project is notifiable
A project is notifiable if the work is scheduled to last longer than 30 working days and have more than 20 workers on site at once at any point, or to exceed 500 person days (one person working one normal shift is a person day). The client notifies before the construction phase: in GB to HSE on form F10, in Northern Ireland to HSENI on form NI10, online only. On domestic work the contractor or principal contractor does it. The notice is displayed in the site office and updated if details change.
Records to keep
- Construction phase plan: current, reviewed and on site.
- Health and safety file information: passed to the principal designer as the job goes on: what the next people working on the structure need to know.
- Excavation inspections: a competent person checks supported or battered excavations at the start of every shift and after anything affecting stability. If not satisfied, they report in writing within 24 hours; the report stays on site until the work ends, then is kept three months.
- Inductions and consultation: no form is prescribed, but signed induction records and toolbox talk notes are the simplest proof.
Ireland: PSDP, PSCS and Safe Pass
Under the Safety, Health and Welfare at Work (Construction) Regulations 2013, the client appoints in writing a Project Supervisor for the Design Process (PSDP) and a Project Supervisor for the Construction Stage (PSCS). The PSCS, often a contractor, does much of the principal contractor’s job: it develops the safety and health plan before work starts, coordinates contractors, site access and welfare, and feeds the safety file.
| Rule | GB and Northern Ireland | Ireland |
|---|---|---|
| Coordinating role | Principal contractor | PSCS |
| Appointment needed | More than one contractor | More than one contractor, a particular risk, or a notifiable project |
| Notifiable | Over 30 working days with more than 20 workers at once, or over 500 person days | Over 30 working days, or over 500 person days |
| Who notifies | Client: F10 to HSE, NI10 to HSENI | Client (AF1) and PSCS (AF2, before work starts) |
| Site plan | Construction phase plan on every project | Safety and health plan where notifiable or a particular risk |
With no 20 worker condition, a small crew on a job of more than 30 working days is notifiable in Ireland but not in GB. The PSCS displays the notified details on site. Irish contractors also have duties with no GB equivalent:
- Safe Pass: craft and general construction workers and on-site security staff need a valid card (a narrow exemption covers some visiting specialist installers). SOLAS issues it for four years; renew by course or a 45 minute computer test.
- Construction skills cards: listed tasks, such as scaffolding, slinging and signalling, excavators, dumpers and locating underground services, need the matching CSCS card.
- First-day checks: the contractor asks to see the cards and confirms in writing to the PSCS that the worker holds them.
- Safety roles: a contractor with normally more than 20 people on a site, or 30 in construction work, appoints a safety officer. The PSCS appoints a full-time safety adviser above 100 on site, and facilitates a site safety representative above 20.
- Records: kept on site (or at the office for jobs under 30 working days) and open to an HSA inspector.
This guide is general information, not legal advice. Check the current position with HSE (GB), HSENI (Northern Ireland) or the Health and Safety Authority (Ireland), and the regulations on legislation.gov.uk or irishstatutebook.ie, before relying on it.
Sources
- legislation.gov.uk: The Construction (Design and Management) Regulations 2015
- legislation.gov.uk: The Construction (Design and Management) Regulations (Northern Ireland) 2016
- HSE: Principal contractors, roles and responsibilities
- HSE: Contractors, roles and responsibilities
- HSE: Commercial clients, roles and responsibilities
- HSE: Are you a small builder?
- HSE: Site rules and induction
- HSE: Second post implementation review of CDM 2015 (March 2026)
- HSENI: Construction (Design and Management) Regulations (Northern Ireland) 2016
- HSENI: Notification of a new construction project (NI10)
- GOV.UK: Design and building work, meeting building requirements
- HSA: Safety, Health and Welfare at Work (Construction) Regulations 2013, S.I. No. 291 of 2013
- HSA: Summary of key duties under the Construction Regulations 2013
- SOLAS: Safe Pass